MAINLINE PROJECTS

Below is a description of some of our completed mainline projects.

PROJECT DETAILS

2,334’ of 4” MP plastic with approx. 9 home services ranging from 200’ to 800’ in length.

UNIQUE CHARACTERISTICS

Project was executed to allow for a road widening. Gas line installed at critical depth of 8’ with two wetland crossings via bore.

PROJECT DETAILS

Replaced 4,268’ of bare steel with 3,750’ of 2” plastic and 49 new gas services.

UNIQUE CHARACTERISTICS

Congested street with heavy traffic. Old neighborhood with undocumented underground utilities and obstructions. 90% of install under sidewalk.

PROJECT DETAILS

Installed 4,040’ of new 4” MP plastic in new subdivision.

UNIQUE CHARACTERISTICS

New development. ASW required to share limited ROW with multiple other contractors performing work related to new development construction.

PROJECT DETAILS

1,000’ of 6” in MP plastic with 1 long side gas service and 2 tie ins.

UNIQUE CHARACTERISTICS

Rural location with limited access to water and dumping to support bore project. 2 critical depth bores at creek crossings. 50-50 mix of open cut and bore used to install.

PROJECT DETAILS

Bored and installed 6,900’ of new 4” plastic.

UNIQUE CHARACTERISTICS

5 challenging critical depth ravines with 3 additional regulated wetland stream crossings. Hard shale at a depth of 2’. Multiple ream passes of increasing size needed to create stable conditions for pullback.